Financial Arrangements and Budget

Incremental Costs: The incremental project costs, not counting project preparation expenditures, to be financed by GEF during three project stages total $US 4.25 million. The amount of $US 8.48 million in co-financing for sustainable development baseline and non-GEF incremental activities has been leveraged during project preparation for the realization of the domestic and local benefits to be realized in conjunction with the securing of global benefits.

Project Budget by Stages
GEF:Project preparationUS$ 233,700
Phase IUS$ 2,100,000
Phase IIUS$ 1,300,000
Phase IIIUS$ 850,000
SubTotalUS$ 4,483,700
Co-financing:Project preparationUS$ 212,000
Phase I:
     GovernmentUS$ 225,710
     Kamchatka Oblast AdministrationUS$ 182,860
     NGOUS$ 470,000
     Bilateral donorsUS$ 1,900,000
Phase II:
     GovernmentUS$ 338,570
     Kamchatka Oblast AdministrationUS$ 274,290
     NGOUS$ 640,000
     Bilateral donorsUS$ 2,400,000
Phase III:
     GovernmentUS$ 225,710
     Kamchatka Oblast AdministrationUS$ 182,860
     NGOUS$ 330,000
     Bilateral donorsUS$ 1,310,000
SubTotalUS$ 8,692,000

Grand total:US$ 13,175,700